Dual-listed Southern Palladium has announced the commencement of its detailed metallurgical and geotechnical drill programmes as part of ongoing field work to support the delivery of the Definitive Feasibility Study (DFS) for the Bengwenyama Platinum Group Metals (PGM) Project scheduled for completion in the first half of 2026.

Bengwenyama DFS Drilling Underway

Four drill rigs have been secured and mobilised to site. First drilling is now underway to obtain a 140kg sample from the UG2 reef for detailed metallurgical study work.

The UG2 sample will be used to determine metallurgical variability across the first stage of the planned development. The results from this sample will also better allow the Company to progress discussions with South African PGM smelters. Once metallurgical drilling is complete, the rigs will move to assist with deeper underground geotechnical drilling, which will be incorporated into field studies to optimise decline and stoping parameters.

A further 2-3 rigs will be added for surface geotechnical drilling, commencing with drilling needed to optimise the first decline development planning, which is scheduled to start at the beginning of October.

The DFS drill programme will comprise around 10,000m drill metres in total and will include infill drilling to further enhance definition of the Maiden JORC Ore Reserve of 6.29Moz at 6.17g/t PGM (6E) at Bengwenyama (refer ASX Announcement 28 October 2024).

This work follows the recent completion of an optimised Pre-Feasibility Study which delivered an estimated after-tax NPV US$857m with a material reduction in peak-funding requirement through a staged development approach (refer ASX Announcement 10 July 2025).

The MRA (Mining Right Application) review process is ongoing. With the achievement of a key milestone in Q2, the Environmental Authorisation approval and the conclusion of the objection period the granting of the Mining Right is anticipated in the near-term.

Managing Director Johan Odendaal, said: “We are pleased to announce the commencement of our DFS drill programme following an extensive period of planning and design. Results from this drill programme will provide important data to further optimise metallurgical processing and mine design for the DFS, which is on schedule for delivery in the first half of 2026. We look forward to providing further project updates over the coming weeks. Environmental approvals have now been obtained, an important prerequisite for the granting of the Mining Right. Final acceptance of the Social and Labour Plan should lead to the grant of the Mining Right within the foreseeable future.”

Highlights

  • Commencement of ~10,000m metallurgical and geotechnical drill programme at the Bengwenyama PGM project, with four drill rigs now operational on site.
  • Metallurgical drill programme designed to collect a 140kg bulk sample from the UG2 Reef for definitive test work, to assess metallurgical variability and for use in concentrate off-take discussions.
  • Additional drill rigs to be mobilised by October to commence surface geotechnical drill programme for design of the first decline and civils of the surface infrastructure.
  • Drill campaign marks delivery of the next phase of Definitive Feasibility Study (DFS) work, in line with Southern Palladium’s stated development strategy for staged mine development.
Pin It

CONTACT

Editor
Nellie Moodley 
Email: mining@crown.co.za
Phone: 084 581 2371

Advertising Manager
Rynette Joubert
Email: rynettej@crown.co.za
Phone: 082 937 1613


More Info