ASX-listed Perseus Mining has continued to make solid construction progress at the Nyanzaga Gold Project in Tanzania in September.

Nyanzaga Gold Project construction update September 2025Highlights included:


✔️ Ngoma town bypass road complete.
✔️ SAG Mill raft concrete foundation poured ahead of schedule with Ball Mill and Gyratory Primary Crusher foundation concrete pours imminent.
✔️ Concrete blinding poured on all process plant critical foundations.
✔️ Big push for the project on Resettlement housing construction, with target to complete by end of October.
✔️ First roofing being installed in the new Camp with first rooms to be opened in October.
✔️ Resource definition drilling continues.